Saltel patch in combination with cement squeeze allows high-pressure/high-volume stimulation, after fixing parted casing section

The client needed to isolate a troublesome parted collar section at 11,068 ft [3,373m] ina 5.5in #23 lbs/ft casing. Since the client had already planned to fracture the well, they needed to regain as much of initial casing integrity possible.
They first performed a remedial cementing job to act both as a barrier and a receptacle, to support a further stainless steel high-pressure inner-lining solution. The client finally selected Saltel Xpandable steel Patch.